Solar Installation Timeline in Lucknow

From Site Survey to Net Metering - Complete Step-by-Step Guide

5-Year Warranty
MNRE Approved
500+ Installations
30-Day Installation
Complete Installation Process Explained

Overview: What to Expect

Installing a solar system in Lucknow is a straightforward process when you work with an experienced installer. The entire journey from initial inquiry to commissioning typically takes 25-35 days, depending on system size and UPPCL processing times.

At Sangya Solar, we handle all aspects of the installation, including paperwork, coordination with UPPCL, and subsidy application. Here is a detailed breakdown of each step:

Phase 1: Consultation & Survey (Day 1-5)

1

Initial Consultation (Day 1)

You contact us via call, WhatsApp, or website form. We discuss your requirements, electricity consumption, and answer initial questions about costs and savings.

2

Site Survey (Day 2-3)

Our engineer visits your property to assess rooftop condition, measure available area, check shadow patterns, evaluate electrical infrastructure, and take photographs for design.

3

Design & Quotation (Day 4-5)

Based on survey, we prepare custom system design including panel layout, inverter selection, and mounting structure. Detailed quotation with all costs, savings projection, and financing options is shared.

Phase 2: Agreement & Procurement (Day 6-15)

4

Agreement & Advance Payment (Day 6-7)

Once you approve the quotation, we sign the installation agreement. 50% advance payment is collected to begin material procurement. We collect necessary documents for subsidy and net metering application.

5

Material Procurement (Day 8-15)

We procure Tier-1 DCR certified panels, inverter, mounting structure, and all accessories from authorized distributors. Quality inspection is done before dispatch to your site.

Phase 3: Installation (Day 16-22)

6

Structure Installation (Day 16-17)

Our team installs the mounting structure on your rooftop. This includes channel frames, clamps, and rail system. Waterproofing is done at all penetration points.

7

Panel & Electrical Installation (Day 18-20)

Solar panels are mounted on the structure. DC wiring connects panels to DCDB (DC Distribution Box). Inverter is installed at designated location. AC wiring connects to your main distribution board.

8

Testing & Commissioning (Day 21-22)

Complete system testing including voltage checks, insulation testing, and safety verification. Inverter is configured and synchronized. Customer training on system operation and monitoring.

Phase 4: Net Metering (Day 23-35)

9

Net Metering Application (Day 23-25)

We submit net metering application to UPPCL along with all required documents, test reports, and single line diagram. Application fee is paid online.

10

UPPCL Inspection & Meter Installation (Day 26-35)

UPPCL inspector visits to verify installation. Upon approval, bi-directional (net) meter is installed replacing your existing meter. Final commissioning report is generated.

Post-Installation: Subsidy & Support

After net metering is complete:

  • Subsidy Application: We upload commissioning certificate to PM Surya Ghar portal. Subsidy is typically credited within 30-90 days.
  • Balance Payment: Remaining 50% is collected after successful commissioning.
  • Warranty Registration: All products are registered with manufacturers for warranty coverage.
  • Ongoing Support: Our team remains available for any queries, monitoring assistance, and maintenance needs.
Documents Required

For Subsidy Application

  • Aadhaar Card (mandatory)
  • Latest Electricity Bill
  • Bank Account Details
  • Passport Size Photo
  • Property Document/NOC

For Net Metering

  • Consumer ID
  • ID Proof
  • Passport Photo
  • NOC (if rented)
  • Test Report (we provide)

Ready to Go Solar?

Get a free consultation and personalized quote today.

Start Your Installation
Free site survey | No obligation

Your information is secure. No spam, ever.

Ready to Start?

Book your free site survey today. No obligation, no pressure.